Merrifield North: faster planning, weaker scrutiny?


05th July 2026
By Peter Ewer, FoMC Committee

The Victorian Government has announced significant changes to the planning process for the Merrifield North Precinct Structure Plan (PSP). This covers land around the Kalkallo Creek, an important tributary of the Merri.

At a briefing by Department of Transport and Planning officers on 11 June, community groups were advised that the process would be substantially streamlined: the co-design process has been removed, agency review during PSP preparation has been discontinued and a planned Melbourne University palaeoecology study of the former Inverlochy Swamp has been cancelled. The revised timetable is expected to reduce the planning process by approximately one year.

Although the full import of these changes is still to be clarified, FoMC has grave concerns about what this means at Merrifield North and for the PSP process in other parts of the catchment. The question is not whether planning should be more efficient, but what has been removed in the pursuit of speed and what the consequences will be.

The concern is not simply that the Merrifield North process has been shortened. Rather, the changes appear to alter the purpose of the PSP itself. Traditionally, a Precinct Structure Plan has been the place where competing public and private interests are reconciled, before urban development proceeds. Housing supply, employment and other land uses must be balanced with biodiversity, flood management, Aboriginal cultural heritage, transport infrastructure, water quality and open space. By reducing opportunities for co-design, agency review and independent scientific investigation, more of these questions appear likely to be deferred to later stages of the urban development process and addressed in a piecemeal, site-by-site basis.

This is particularly important because many environmental issues cannot easily be managed after the strategic planning stage has concluded. Flood behaviour, catchment hydrology and water quality are cumulative processes operating across an entire landscape. They are not confined to individual subdivisions, or planning permits.

The Department’s presentation on 11 June emphasised that technical studies would continue, that integrated water management remained an objective and that detailed work on drainage, biodiversity and sodic soils would still be undertaken. Those commitments are welcome. The same presentation also indicated that the Draft PSP would be released while some technical work remained incomplete, with “issue resolution” continuing after exhibition. We are seeking clarification about how meaningful public consultation could occur before the full suite of technical information was available and how significant changes arising during the following eleven months would be incorporated into the process.

The broader context is also difficult to ignore.

Over recent months, Victoria’s major property organisations have all argued that the PSP system should be ‘streamlined.’ The Property Council of Australia has called for significantly shorter PSP timeframes, fewer delays from referral authorities, earlier resolution of agency disagreements and greater ministerial authority to resolve outstanding issues. The Urban Development Institute of Australia has argued that PSPs have become increasingly complex and has recommended reducing land quarantined for drainage, environmental protection and other purposes, while pushing finalization of drainage requirements to later permit processes. The Housing Industry Association has similarly called for faster planning decisions and a reduction in regulatory burdens affecting greenfield development.

In the light of this powerful lobbying, it is difficult to overlook the extent to which the government’s changes align with the direction advocated by the development industry.

This matters because the environmental consequences of planning decisions do not disappear simply because they are removed from the strategic planning process. They are often transferred into less visible parts of the system: Development Services Scheme modelling; engineering approvals; Construction Environmental Management Plans; and permit conditions. While these are all important mechanisms, they attract far less public scrutiny than a Precinct Structure Plan and are often difficult for the community to access or evaluate.

The result is that strategic environmental questions increasingly become technical compliance questions.

For Merrifield North, this is particularly significant. Flood management depends upon complex catchment-scale modelling. Sodic soils – those which effectively ‘dissolve’ once topsoil is disturbed – are well-known risks to water quality. What is known as the Inverlochy Swamp – part of the Kalkallo Creek catchment — has ecological, hydrological and cultural significance extending beyond how many warehouses can be built on it. These are not simply engineering matters: they are questions about how an entire catchment will function as urbanisation proceeds.

Effective planning requires more than satisfying the development lobby. It demands public confidence, which depends upon transparency, independent expertise and sufficient opportunity for agencies, Traditional Owners, scientists and the community to test the evidence before decisions are made.

The announced changes raise legitimate questions about whether that balance has shifted too far towards speed at the expense of scrutiny.

The coming public consultation therefore assumes even greater importance. If strategic planning is to be accelerated, then the quality of the evidence supporting those decisions—and the opportunity for genuine public examination of that evidence—becomes more important, not less.

The challenge for government is therefore not simply to demonstrate that Merrifield North can be planned more quickly. It is to demonstrate that it can still be planned well.

constraints_and_issues.png
Victorian Planning Authority, Merrifield North, Wurundjeri Woi-wurrung Country,
Precinct Structure Plan Pitching summary report, August 2025, p.11